1.  The chain of activities in a plan that must begin and end on time in order to achieve project milestones and execute the project on schedule is a/an:
a.  absolute agenda
b.  critical path
c.  schedule timeline
d.  crucial series

2.  The process that must be followed to utilize a project management procurement plan are:  plan, ___________, administer, and close
a.  conduct
b.  research
c.  negotiate
d.  evaluate

Answers: 
1.  b
2.  a
 
 